Etha participated in Finland’s largest deal in wind power as a due diligence consultant.

In spring 2020, Etha performed due diligence services in Finland’s largest wind power deal to date. In the deal, renewable energy investor Exilion acquired 11 wind farms with the total capacity of 315 MW. This is equivalent to 14 % of the existing wind power in Finland.

Etha was involved as the technical due diligence consultant and delivered the project in the spring of 2020.

The scope included:

  • Permitting review
  • Grid connection review
  • Turbine walkdowns
  • Valuation opinions

The project was managed by Etha’s Caroline Kullbäck and included a team of eight persons. Both in-house personnel and external experts were represented in the team.

Exilion is owned by Finnish earnings-related pension providers. Read more about the transaction on Exilion’s website.

Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognizing you and your language when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookies should be enabled at all times so that we can save your preferences for language and cookie settings.

3rd Party Cookies

This website uses Google Analytics, Leadfeeder and Microsoft Clarity to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website